Introduction
The Cyclone 4400 Meter Lubrication System (MLS) is engineered to deliver systematic lubrication to turbine meters, enhancing measurement accuracy and longevity. It functions in three modes: time-based injection, time-based injection with differential pressure switch (DPS-2), and proportional-to-flow injection.
Operation Specifications
The system operates with an injection pump at pressures ranging from 15 to 1500 psi and temperatures between -30°F and +140°F. It features a 6 oz polycarbonate and anodized aluminum oil reservoir. The controller is powered by a lithium battery pack with a two-year reserve.
Theory of Operation
The Cyclone 4400 employs a pneumatically operated, positive displacement pump and a Z-65/6.1H timer/controller. It injects lubricant at set intervals or in response to flow, using a solenoid valve to manage actuation gas.
System Accessories
Optional accessories include external power, solar power, and a stainless steel check valve, enhancing system flexibility and efficiency.
Application
Ideal for field maintenance of turbine meters, the system ensures unrestricted movement and precise measurement. It accepts pulses from various devices and operates in different modes to meet specific requirements.
System Installation
The Cyclone 4400 should be mounted vertically near the meter, requiring a 1/4" NPT pipeline gas connection and a 1/8" discharge tubing connection to the meter injection port. An in-line check valve is recommended at the injection port.
Injector Maintenance
Regular maintenance involves checking and replacing batteries, adhering to a preventative maintenance schedule, and following provided procedures for pump disassembly and assembly.
Troubleshooting
The manual provides detailed troubleshooting steps for timer mode, mechanical operation tests, and input tests, including fuse replacement and counter mode diagnostics.
Diagrams
Diagrams of the C44 pump, YZ filter regulator, Z-65 controller, and DPS-2 are included to aid installation and maintenance.
System Control and Electronics Overview
The Cyclone 4400MLS system uses a Z-65/6.1H controller to manage the C-44 pump's actuation rate, configurable for dry contact or voltage pulse inputs with specific mode switch settings.
Setting Input Parameters
The Z-65 controller can be configured for proportional-to-flow or proportional-to-time operations, with settings calculated based on pump displacement, desired injection rate, and pulses per volume metered.
Operational Check and Leak Testing
Before operation, ensure secure tubing connections and check for leaks using a liquid leak detector. Adjust the filter/regulator as needed and fill the oil reservoir. Test for leaks and functionality by allowing the injector to operate until oil is present at the purge orifice and pressure builds on the protector gauge.
Injector Maintenance
Regular maintenance includes biannual cleaning and inspection of the injector pump, checking the filter element every six months, and monthly battery testing. A list of recommended spare parts is provided.
Pump Rebuild Procedures
Detailed steps for disassembling and assembling the pump are provided, emphasizing proper lubrication and alignment during reassembly.
Battery Test and Replacement
Test battery condition by setting mode switches and observing LED indicators. Replace the battery by removing it from the Z-65 controller and installing a new pack, ensuring correct wire placement.
Troubleshooting
Diagnostic modes are available for testing mechanical operation, DPS-2 functionality, and the LCD stroke indicator. Adjust mode switches and time settings to enter diagnostic modes for solenoid output rates and stroke counter functionality.
Range Setting
The Z-65/6.1H timer/counter has two range settings: 'xx hours' or 'x100 counts' (jumper far left) and 'x.x hours' or 'x10 counts' (jumper center position).
Fuse Replacement
If the Z-65 does not power up, replace F1. If the stroke light is on but the solenoid does not activate, replace F2.
Troubleshooting
For counter mode, set mode switches to positions 1 and 3 on, 2 and 4 off. Enter diagnostic mode by setting count switches to 00. For dry contact input, mode switch 4 should be off; for voltage pulse input, it should be on. LEDs indicate pulse reception.
Mechanical Assembly
Key components include the C-44 Pump, Calibration Oil Reservoir, Filter Regulator, and Solenoid. Ensure system actuation pressure is at least 15 psi and oil level is visible. Follow the diagram for testing.
Diagrams
Diagrams for the C-44 pump, YZ filter/regulator, Z-65 Controller, and DPS-2 are included, detailing parts and assembly instructions.
Warranty
YZ Systems provides a 1-year warranty against defects in materials and workmanship, limited to the U.S. and Canada, with remedies including product replacement or repair efforts.
See more

Catalog excerpts

Cyclone 4400-2

THE CYCLONE 4400 INSTRUCTION & OPERATING MANUAL Version: 05012002 Rev.1

 Open the catalog to page 2
Cyclone 4400-4

SECTION 1: FIRST THINGS TO KNOW ABOUT THE MLS Operation Specifications Injection Pump Operating Pressure: Actuation Pressure: Displacement: Operating System Temperature: Service Connections: Actuation Gas Inlet: Lubricant Discharge: 1/4” NPT Female 1/8” S/ST tube, Ferrule Oil Reservoir Material: Capacity: Compatible Lubricants: Polycarbonate & Anodized Aluminum 6 oz. (175 cc) (1250 injections) Chemlube, Anderol, 5w or equivalent Controller Power Supply: Battery Reserve: Timer Accuracy: Display: Flow input: Continuous: Minimum Pulse Width: Pulse Type: Lithium battery pack 2 years (1 stroke/hr)...

 Open the catalog to page 4
Cyclone 4400-5

SECTION 1: FIRST THINGS TO KNOW ABOUT THE MLS Theory of Operation The Cyclone 4400 MLS is a pipeline mounted system which uses the pneumatically operated, positive displacement Cyclone 4400 pump, the Z-65/6.1H timer/controller, the YZ filter/regulator and a low power solenoid valve to deliver injections. The 4400 provides three modes of operation: A. Time-based injection: In this mode of operation, the 4400 injects lubricant into the meter at regular time intervals. The volume of injection is preset at .140 cc/stroke. The Z-65/6.1H controller operates as a recycling timer, periodically energizing...

 Open the catalog to page 5
Cyclone 4400-6

SECTION 1: FIRST THINGS TO KNOW ABOUT THE MLS Application One of the difficulties in maintaining turbine meters in the field is that they require lubricant for the unrestricted movement of the turbine, and for measurement accuracy. Maintaining the lubricant level in meters is a problem that has existed for a very long time. Today, at YZ Systems, we have the solution in the Cyclone — Meter Lubrication System 4400. Capable of accepting pulses directly from a meter, index pulser, electronic corrector, or flow computer, the Cyclone can operate in Proportional-to-flow or time-based injection modes....

 Open the catalog to page 6
Cyclone 4400-7

NSTALLA ALLATION SECTION 2: SYSTEM INSTALLATION System Components The primary components of the Cyclone 4400 MLS (Meter Lubrication System) are illustrated below. Solenoid Valve Lubricant Reservoir Factory Mutual System Approved Serial Number Plate Filter Regulator Actuation Gas Manifold (1/4" NPT Inlet) Mounting Plate Lubricant Discharge Cyclone Protector

 Open the catalog to page 7
Cyclone 4400-8

SECTION 2: SYSTEM INSTALLATION NSTALLA ALLATION Injector Location 1. The injector unit should be located as close to meter as possible. In addition, discharge tubing should be kept as short as possible. 2. The injector unit is designed to mount to a 2" pole. The recommend mounting configuration is shown below. Lubricant Discharge Pipline Flow Turbine Meter (By Customer)

 Open the catalog to page 8
Cyclone 4400-9

NSTALLA ALLATION SECTION 2: SYSTEM INSTALLATION Injector Installation 1. The Cyclone 4400 should be mounted in a vertical position. 2. The Cyclone 4400 requires a 1/4" NPT pipeline gas connection. 3. The 1/8" discharge tubing should connect to the meter injection port. An in-line check valve should be installed at the injection port. Actuation Gas Lubricant Discharge (1/8" Tubing) In-Line Check (By Customer) Isolation Valve (By Customer) Isolation Valve (By Customer) Turbine Meter (By Customer)

 Open the catalog to page 9
Cyclone 4400-10

NSTALLA ALLATION SECTION 2: SYSTEM INSTALLATION (Optional) DPS-2 Installation 1. With the low pressure supply valve and the high pressure supply valve closed, connect the DPS-2 to the orifice connection tubing. 2. Open the equalization valve. Black 3. Open the low pressure supply valve or the high pressure supply valve. IMPORTANT NOTE: Factory Mutual System Approved Do not open either the low pressure supply valve or the high pressure supply valve without ensuring that the equalization valve is open. Failure to do so may damage the DPS-2's internal components. 4. Open the other supply valve....

 Open the catalog to page 10
Cyclone 4400-11

ONTROL SECTION 3: SYSTEM CONTROL LECTRONICS ELECTRONICS Solenoid Valve Lubricant Reservoir Factory Mutual System Approved Serial Number Plate Filter Regulator Actuation Gas Manifold (1/4" NPT Inlet) Mounting Plate Lubricant Discharge Cyclone Protector Actuation Gas Lubricant Discharge (1/8" Tubing) In-Line Check (By Customer) Isolation Valve (By Customer) Isolation Valve (By Customer) Turbine Meter (By Customer)

 Open the catalog to page 11
Cyclone 4400-12

ONTROL SECTION 3: SYSTEM CONTROL LECTRONICS ELECTRONICS Setting Input Parameters Z-65 Set-Up Proportional-To-Flow In this mode of operation, the Z-65 controller is used as a dividing counter to control the rate at which the pump is actuated. The desired time between pump strokes is controlled by the host computer or output device that will give an input pulse to the Z-65 controller. 1. Determine if the incoming input is either a dry contact or voltage pulse. Factory Mutual System Approved 2. If the input is a dry contact: a. Terminate the incoming connections to the Z-65/6.1H terminal strip (see...

 Open the catalog to page 12
Cyclone 4400-13

ONTROL SECTION 3: SYSTEM CONTROL LECTRONICS ELECTRONICS Calculate the counter setting using the following chart: 2. Desired injections lubricant per volume of flow (cc/MMCF or cc/MCM) 3. pulses/volume metered (pulses/MMCF or pulses/MCM) Example #1: English Gas Flow Units pump displacement injection rate pulses per volume metered Example #2: Metric Gas Flow Units Example #1 counter setting Example #2 counter setting If the calculated counter setting is less than 10 or greater than 9900, the pulses per volume metered will need to be adjusted. This can be programmed in most flow meters to the desired...

 Open the catalog to page 13
Cyclone 4400-14

ONTROL SECTION 3: SYSTEM CONTROL LECTRONICS ELECTRONICS 2. Set the timer dials on the Z-65/6.1H to the injection rate from step 8.1. TIME XX, X.X (HR.) COUNT x100, x10 18 hours IMPORTANT NOTE: The time (18 hours) above corresponds to the dial setting shown for the Z-65/6.1H model with the timer range setting in the factory position (jumper on the two left pins). See page 21 Timer Range Setting. 3. Turn mode switch 1 to on. 4. Turn mode switch 2 to on. 5. Turn mode switch 3 to on. 6 .Turn mode switch 4 to off. 7. Press the test button once to initiate the timer sequence. YZ

 Open the catalog to page 14
Cyclone 4400-15

SECTION 3: SYSTEM CONTROL ONTROL ELECTRONICS LECTRONICS Setting Input Parameters Z-65 Set-Up Proportional-To-Time w/DPS-2 Option 1. Calculate the injection rate using the following 30 day chart: 2. Set the timer dials on the Z-65 to the determined time from step 1 above. TIME XX, X.X (HR.) COUNT x100, x10 18 hours 3. Turn mode switch 1 to on. IMPORTANT NOTE: 4. Turn mode switch 2 to on. The time (18 hours) above corresponds to the dial setting shown for the Z-65/6.1H model with the timer range setting in the factory position (jumper on the two left pins). See page 21 Timer Range Setting. 5. Turn...

 Open the catalog to page 15
*Prices are pre-tax. They exclude delivery charges and customs duties and do not include additional charges for installation or activation options. Prices are indicative only and may vary by country, with changes to the cost of raw materials and exchange rates.