Project OverviewSociedad Contractual Minera El Abra is undertaking a turn-key project for an overland
conveyor system at the El Abra Open Pit Mine in Chile.
Project Specifications- Overland Conveyor 1: Length of 500 meters, belt width of 1,600 mm, drive power of 4 x 450 kW, with a theoretical output of 5071 m3/h or 8620 t/h.
- Overland Conveyor 2: Length of 5500 meters, belt width of 1,600 mm, drive power of 5 x 900 kW, with a theoretical output of 5071 m3/h or 8620 t/h.
- Overland Conveyor 3: Length of 9525 meters, belt width of 1,600 mm, drive power of 4 x 1600 kW, with a theoretical output of 5071 m3/h or 8620 t/h.
Project Schedule
The commissioning of the project was completed in 1996.