1. Catalogs
  2. Smit Transformatoren
  3. The technical developement of SMIT Transformers

The technical developement of SMIT Transformers

The technical developement of SMIT Transformers
1 / 10 PagesView full catalog

The technical developement of SMIT Transformers

Product catalog summary
Introduction and Early Developments (1885-1916)
The document provides a historical overview of Smit Transformers, founded by Willem Smit in the late 19th century. A significant milestone was the construction of the first Dutch three-phase power transformer in 1900.
Establishment of the Transformer Factory (1910-1916)
In response to growing demand, Smit established a dedicated factory in Nijmegen in 1913. Despite World War I challenges, the company produced transformers up to 1250kVA.
The Nolen Era (1916-1955)
Under Prof. Dr. Ir. Henry George Nolen, the company advanced significantly, increasing transformer HV ratings from 10kV to 220kV and power ratings from 1.25MVA to 200MVA. Innovations included tap changers and higher voltage ratings.
Post-War Expansion and Standardization (1940-1955)
Post-World War II, there was a surge in transformer demand. The company developed basic designs customizable for various specifications despite a lack of standardization.
The New Era (1955-Present)
Key figures like Mr. Wildeboer, Mr. Hulsink, and Mr. Kroon contributed to growth. Technological advancements included the use of cold rolled grain-oriented electrical steel, improved insulation, and better transformer oil.
Technological Advancements (1955-1975)
New materials and manufacturing techniques improved transformer design, reducing losses and noise, and allowing higher field strengths and operating temperatures.
Conclusion
The document concludes by emphasizing the importance of innovation and adaptation in meeting the growing demands of the electrical engineering sector.
Introduction of Computer Systems and CAD (1980-1990)
Nijmegen implemented its own computer system in 1980, reducing design errors. By 1990, the Engineering Department transitioned to a CAD system with 3-D solid modelers.
Innovations in Transformer Design (1975-1980)
Smit introduced independent winding clamping construction, enhancing resistance to short circuits and simplifying installation.
Voltage Calculation and Digital Registration (1986-1988)
Methods to calculate oscillatory voltage improved lightning impulse voltage strength. Digital registration allowed high-resolution oscillogram recording and Fourier analysis.
ISO 9001 Certification and Temperature Measurement (1988-1990)
Smit became the first transformer factory to achieve ISO 9001 certification and advanced direct winding temperature measurement using glass fiber optics.
Significant Projects
  • 1968-1970: Delivered single-phase units for the Netherlands' national network, forming a 450 MVA three-phase bank.
  • 1976: Built a 780MVA generator step-up transformer for PNEM.
  • 1983: Supplied a 500MVA transformer to Danish NESA.
  • 1987: Delivered a 607MVA transformer to NYPA.
  • 1989: Developed a 725MVA transformer for the Hemweg power plant.
  • 1993: Built two 750MVA autotransformers for the Zwolle/Eemshaven project.
  • 1995-1996: Supplied high-voltage transformers to Arizona Public Services and Ontario Hydro.
  • 2000: Designed the world's largest Phase Shifting Transformers for TenneT.
See more

Catalog excerpts

The technical developement of SMIT Transformers -1

F i r st in Holland built transformer 40 k.V.A. 1050/120V/, delivered to Dutch R ailway together with a g enerator. Source: Anniversary book Smit Slikkerveer >

 Open the catalog to page 1
The technical developement of SMIT Transformers -2

project of 1886, Smit also had a special bond with Nijmegen, despite it being a city very distant from Slikkeveer, both from a geographical and a cultural point of view. Operations in Nijmegen were started in 1913 with a workforce of approximately 50 employees. The provincial electric companies used an HV network based on 10kV, and in the smaller towns lower voltages of 3.5kV and 6kV were utilised. However, there existed no national standard voltage levels. In the first year the largest capacity transformer manufactured was rated at 1250kVA, with an average capacity of about 30kVA. During WW...

 Open the catalog to page 2
The technical developement of SMIT Transformers -3

The Nolen Era, 1916-1955 Prof. Dr. Ir. Henry George Nolen must be regarded as the forefather of transformer technology in Smit Transformers. During his employment, transformer HV ratings increased from 10kV to 220kV and the power ratings increased from 1.25MVA to 200MVA. In 1925 he was appointed Technical Manager of Smit Transformers and he obtained his doctorate with distinction, with a thesis based on Transformer FieldsӔ with Professor Feldman, whom he succeeded in 1937 as Professor. He remained attached to Smit Transformers as Technical Manager until his retirement in 1955, and even after...

 Open the catalog to page 3
The technical developement of SMIT Transformers -4

windings were then lifted on site into the tank, finished and dried, and the final assembly of the transformer took place on site. In 1948, on the occasion of the firm's 35th anniversary, Professor Nolen wrote about this tour de force: I learned a hard lesson then, namely that it is absolutely necessary to always have the building, means of transport, dryers and test devices needed for new objects before they are sold. This has become our guiding principleӔ. Wise words indeed. By 1921 Smit Transformers already had test equipment which was modern for those days and which was already prepared for...

 Open the catalog to page 4
The technical developement of SMIT Transformers -5

followed in 1935 with the use of 150kV rated transformers in the Province of Limburg, though with a relatively small capacity of 6000kVA.The electrification of the railway network at 1500V DC voltage was developing successfully in 1937. The requirements of the transformers were high. Complex Yyd connected designs with 7.5 degree swing windings and extremely small tolerances for the short-circuit voltage were required, for use in connection with the mercury-arc rectifiers. The original capacity amounted to 1200kVA and increased to 2200 kVA in later years. In 1939, the cities of Rotterdam and The...

 Open the catalog to page 5
The technical developement of SMIT Transformers -6

During this period, basic designs were made which could be easily adjusted to the customer's specification. There was also a large amount of technical and project- based consultation with customers occurring. Although it was not yet defined as such then, a co-engineering culture was developing, which paid off in the next period in which more complex orders were obtained. However, market demand resulted in few memorable projects during this period. In 1955, Professor Nolen went into a well-deserved retirement, which marked the end of this era. The New Era 1955-Present The key technical figures...

 Open the catalog to page 6
The technical developement of SMIT Transformers -7

19601965: The quality of the transformer oil improved greatly (higher breakdown voltage, higher degradation temperature and less ageing) as a result of which higher field strengths could be incorporated into the transformer designs. From 1995, it became more common to add inhibitors to the oil in order to provide it with even better properties. 1965֖1975: Complex calculations by hand gave gradually way to various types of calculators. At first a kind of Hollerith-like cards were used, which were processed in Delft; with the calculation result returned by post to Nijmegen. Between 1975 and 1980...

 Open the catalog to page 7
The technical developement of SMIT Transformers -8

During 1968-1970, the SEP (Association of Electricity-Generating Undertakings) started with the construction of a national interconnected network within the Netherlands at the 380kV level. Smit Transformers delivered the first single-phase units rated at 150 MVA, 380/ winding hotspot was situated, and the difference between the hotspot temperature and that of the average winding temperature could be easily seen. This resulted in designs featuring reduced winding hotspot temperatures and a corresponding extended life expectancy. √ 3//150/ √ 3//50kV, thus forming a three-phase bank of 450 MVA,...

 Open the catalog to page 8
The technical developement of SMIT Transformers -9

measurements of noise levels were carried out in the customer's presence, with the result that the noise requirements were completely satisfied. In 1987, one of our most loyal U.S. customers, NYPA, a firm we have supplied since 1978, granted us the order for the so far largest U.S. generator transformer, 607MVA 345/20.3 kV, 60 Hz. For the transformer factory acceptance tests, Smit Transformers have their own generators, which are capable of generating at either 50Hz or 60 Hz by means of a gearbox located between the motor and generator. In 1989, the designers faced a real challenge. UNA wished...

 Open the catalog to page 9
The technical developement of SMIT Transformers -10

project was completed to the full satisfaction of the customer. At the time these were the largest PSTҒs in the world. Further information about Willem Smit: www.willemsmithistorie.nl 10 >

 Open the catalog to page 10

All Smit Transformatoren catalogs and technical brochures

*Prices are pre-tax. They exclude delivery charges and customs duties and do not include additional charges for installation or activation options. Prices are indicative only and may vary by country, with changes to the cost of raw materials and exchange rates.