Overview of Sarens Launching Unit (SLU)
The Sarens Launching Unit (SLU) was specifically designed for the skidding of the Millau bridge deck in France in 2003. The bridge deck, measuring 27 meters in width and 2460 meters in length, with a total weight of 290,000 tons, was skidded using this system. The SLU was installed on seven temporary support structures, known as Sarens Multi Lifting Towers (SMLT), reaching a maximum height of 168 meters. The system had a total pushing capacity of 7,680 tons during the final skidding stages.
Specifications
  • Each SLU consists of a lifting cylinder with a capacity of 250 tons.
  • Designed to launch vertical loads up to 2,000 tons.
  • Equipped with two 60-ton cylinders for retracting and launching the deck up to 600 mm.
  • Can be used for both retracting and extending the launching cylinder.
Launching Process
  1. Initial Position: The launching cylinder is extended, and the pushing cylinder is retracted, with the load supported by the fixed support.
  2. Lifting: The lifting cylinder extends, transferring the load to the pushing block.
  3. Launching: The launching cylinder retracts, moving the object with a maximum stroke of 600 mm.
  4. Lowering: The lifting cylinder retracts, transferring the load back to the fixed support.
  5. Final Position: The process concludes with the object in its final position.
See more

Catalog excerpts

Sarens Launching Unit-1

Sarens Lauching Unit nothing too heavy, nothing too high

 Open the catalog to page 1
Sarens Launching Unit-2

SARENS LAUNCHING UNIT CSLUJ The system was build for the skidding of the deck of the bridge of Millau in France in 2003. From both sides the deck of 27m wide and 2460m long (total bridge weight of 290.000 ton) was skidded with the Sarens Launching Unit. The launching system was installed on top of 7 temporary support structures (SMLT: Sarens Multi Lifting Tower) with a maximum height of 168m. During the last steps of the skidding the launching units had a total pushing capacity of Basically, each launching unit consists of a lifting cylinder with a capacity of 250 ton. One SLU is designed to...

 Open the catalog to page 2
Sarens Launching Unit-3

SARENS LAUNCHING UNIT CSLUJ Launching process phase 1: initial position The launching cylinder is extended, the pushing cylinder is retracted. All load is supported by the fixed support of the launching unit. By extending the lifting cylinder, the load is transferred from the fixed support to the pushing By retracting the launching cylinder, the object is moved with a maximum stroke of 600mm. nothing too heavy, nothing too high

 Open the catalog to page 3
Sarens Launching Unit-4

SARENS LAUNCHING UNIT CSLUJ By retracting the lifting cylinder, the load is transferred from the pushing block to the fixed phase 5: final position nothing too heavy, nothing too high