INSTALLATION PREPARATION
Open the catalog to page 1STAGE I Foundation Construction The machine must be assembled on a previously made concrete foundation using the steel anchors provided in the set. A trench should be dug with dimensions 40cm x 20cm and a depth of 90cm. Place the anchors in the trench, ensuring that the top plate connecting all 4 anchors is level. The plate should be flush with the ground level and represent the top level of the foundation. Between the anchors, lay the power cable in a corrugated plastic cable sleeve. Leave an excess of cable above ground level, with a minimum length of 200cm. Stabilize the entire setup and pour...
Open the catalog to page 2Foundation anchors with power cable cable shield power cable ground level power cable
Open the catalog to page 3STAGE II Above-ground assembly of the machine no sooner than 7 days after foundation construction Assembly of the connector element on the concreted parts. The distance from the bottom of the connector element to the foundation level should be approximately 25mm. Assembly of the connector element
Open the catalog to page 4Anchors for embedding in the ground At the installation site, dig a hole with dimensions of 40x200mm and a depth of 900mm. After stabilizing the anchors, insert a conduit for the power cable and fill with concrete of at least class B20
Open the catalog to page 5Poziom terenu