Thank you for purchasing (or planning to purchase) our innovative device! We are convinced that with the help of our product - the FUKA dryer - you will take your car wash to the next level. To ensure long and trouble-free use of our product, the final installation site of the FUKA dryer must be properly prepared. Here are the basic requirements for preparing such a site: Preparing the electrical connection The place prepared for the installation of the device must be supplied with stable power supply with minimum voltage of 230V (1 phase) using a cable of the appropriate crosssection: • for...

Open the catalog to page 2
FUKA - PREPARATION FOR INSTALLATION CONCRETE FOUNDATION - 3

Attaching the machine to the ground In order to ensure maximum stability of the device during normal use, a proper foundation for the installation should be prepared in advance. Steel anchor + concrete foundation At least 7 days prior to the scheduled installation of the device, the concrete foundation must be constructed in accordance with the specifications below and with use a steel anchor previously supplied by the device manufacturer. To do this, you need to make a trench measuring minimum 70cm x 50cm and 120 cm deep. The power cable must be led into the trench in accordance with the...

Open the catalog to page 3
FUKA - PREPARATION FOR INSTALLATION CONCRETE FOUNDATION - 5

height: 3,2 m arm lenght: 2,9 m housing width: 0,5 m InnoSync s.r.o. Fuka – Mind Blowing Solutions Rybna 716/24, 110 00 Prague, Czech Republic mail: contact@airfuka.com tel: +420 776 747 716 www.airfuka.com