Introduction
The document discusses the implementation of the JetSnake system by OC Robotics for Bouygues Travaux Publics, aimed at cleaning and inspecting the cutting head of a tunnel boring machine (TBM) beneath the Port of Miami.
Objectives
The primary objective was to test a proof of concept design in a real-world scenario. The project faced compressed timescales and significant technical risks, requiring the design of a pressure control system, environmental sleeving, increased reach, and integration within a TBM.
Business Case
The project provided an opportunity to test the JetSnake system in challenging conditions, including high pressure, temperature, humidity, and environmental hazards. Future tunnel pressures are expected to increase, making human entry difficult and costly.
JetSnake System Specifications
The JetSnake features a multi-jointed snake-arm with a 400bar water jet, high-quality zoom camera, and lamps for inspection. It has a diameter of 125mm, a horizontal reach of 3m, and a payload capacity of 5kg. The arm is sleeved for protection and operates in hyperbaric conditions up to 3.5 bar.
Operation
The system was deployed in Miami in October 2012, with setup and testing completed swiftly. It was successfully integrated into the TBM, demonstrating effective operation along complex paths. The system met trial objectives, proving its potential for future deep tunneling projects.
Conclusion
The JetSnake system enhanced maintenance capabilities by allowing inspections in areas inaccessible to humans, optimizing TBM usage. It identified damage that would have required extensive manual inspection, with live video feedback enabling remote monitoring by senior managers.
See more

Catalog excerpts

JetSnake - TBM Cleaning and Inspection-1

Construction case study Snake-arms for tunnel boring machines OC Robotics supplied Bouygues Travaux Publics with a snake-arm to clean and inspect the cutting head of a tunnel boring machine (TBM) beneath the Port of Miami. DEFINE Objectives Business case As tunnels are dug deeper, maintenance becomes increasingly hazardous for people. In Miami the ambient pressure was 3.5 bar, at 50degC, with 100% humidity and considerable amounts of salt, mud and rock. In the future tunnel pressure will increase to 12bar making human entry extremely challenging and expensive. The Port of Miami project provided an opportunity to take the proof of concept design directly to site test. The timescales were compressed and the technical risk was considerable. The implementation required design of a pressure control system, sleeving for the environment, increased reach and integration within a TBM. DESIGN The JetSnake system includes a multi-jointed nose-following snake-arm. The head of the snake-arm contains a 400bar water jet, a high-quality zoom camera and lamps for inspection. (Fig 3). The cameras and lights operate whilst water jetting. The snake-arm robot has a diameter of 125mm and a fully extended horizontal reach of 3m (excluding the wrist and tools), with a payload of 5kg. The arm was sleeved to protect it from hazardous environments and has a pressurisation system up to 3.5 bar +/- 0.01bar to operate in hyperbaric conditions. Fig 2. Testing of JetSnake system Tool Actuator pack Fig 1. JetSnake (without sleeving) Fig 3. JetSnake tool – water jet, camera and lights DELIVER Operation The JetSnake system arrived in Miami in October 2012 and was set up and operated in a test area within an hour. Installation of the system in the TBM took less than 24 hours with a further day for commissioning. The head motion, cameras and the ability to follow a path were all tested successfully. The arm was deployed along both straight and curved paths within the complex TBM cutting head geometry. (Fig 5) TBM production scheduling allowed two extended windows of JetSnake operation. JetSnake was able to identify damage which would otherwise have involved a lengthy manual inspection. Live video feed back to Paris enabled senior managers to watch the inspection at first hand. Fig 5 JetSnake water jetting – inside TBM Fig 4. Disc cutter before and after water jet cleaning Conclusion The proof of concept JetSnake system achieved the trial objectives and BOUYGUES TRAVAUX PUBLICS intend to use the solution in future deep tunnelling projects. The Jet-Snake allows inspections even when and where it is not possible to send workers in the excavation chamber. This enhances the maintenance organization and play a part in the optimization of the use of the TBM

 Open the catalog to page 1

All OC Robotics catalogs and technical brochures

  1. LaserPipe

    45  Pages

  2. LaserPipe

    1  Page

  3. Ringhals

    2  Pages

  4. LaserSnake2

    2  Pages

*Prices are pre-tax. They exclude delivery charges and customs duties and do not include additional charges for installation or activation options. Prices are indicative only and may vary by country, with changes to the cost of raw materials and exchange rates.