1. Catalogs
  2. DAWSON CONSTRUCTION PLANT LIMITED
  3. UNIVERSAL SHEET PILE THREADER

UNIVERSAL SHEET PILE THREADER
1 /28Pages

UNIVERSAL SHEET PILE THREADER

UNIVERSAL SHEET PILE THREADER
1 /28Pages

Catalog excerpts

UNIVERSAL SHEET PILE THREADER-1

UNIVERSAL SHEET PILE THREADER OPERATORS INSTRUCTION MANUAL AND SPARE PARTS LIST INNOVATIVE PILING EQUIPMENT HYDRAULIC PILING HAMMERS EXCAVATOR MOUNTED VIBRATORS EXCAVATOR MOUNTED DRILLS QUIET, VIBRATIONLESS PUSH-PULL PILING PILE EXTRACTION SHEET PILE GUIDE FRAMES SHEET PILE CAPPING SYSTEMS CFA CLEANERS PILE POINTS & SPLICERS HANDLING / LIFTING www.dcpuk.com

 Open the catalog to page 1
UNIVERSAL SHEET PILE THREADER-2

USPT DAWSON CONSTRUCTION PLANT CONTACTS Dawson Construction Plant Ltd Chesney Wold. Bleak Hall, Milton Keynes, MK6 1NE, England Tel: +44 (0) 1908 240300 Fax: +44 (0) 1908 240222 www.dcpuk.com --------------------------------------------------------------------------------- --------------------------------------------------------------------------------- --------------------------------------------------------------------------------- --------------------------------------------------------------------------------- ---------------------------------------------------------------------------------...

 Open the catalog to page 2
UNIVERSAL SHEET PILE THREADER-3

USPT DAWSON CONSTRUCTION PLANT 1. Contacts 2. Contents 3. Introduction 4. Weights and Dimensions 6. Initial assembly on the units 8. Setting the rollers to fit the pile section 10. Setting the threading head 12. Method of Operation 14. Safety 16. Maintenance 18. Parts list 22. Set up drawing Under separate cover: · Individual Test Certificate & Thorough Examination if required. · E.C. Declaration of Conformity CONTENTS

 Open the catalog to page 3
UNIVERSAL SHEET PILE THREADER-4

USPT DAWSON CONSTRUCTION PLANT INTRODUCTION The Dawson Universal Sheet Pile Threader has been developed to enable a safe, easy and productive method of pitching sheet piles. The need for a “top man” is eliminated as all operations can be performed at ground or top frame level. The Universal Sheet Pile Threader can be set up for virtually all Larssen and Z section sheet piles, and once set correctly will quickly interlock the piles with one simple movement. Care should be taken during the set-up procedure to ensure that each adjustment is accurately set, extra time spend here will be saved tenfold...

 Open the catalog to page 4
UNIVERSAL SHEET PILE THREADER-5

USPT DAWSON CONSTRUCTION PLANT WEIGHTS AND DIMENSIONS Complete assembly - 51Kg Complete assembly in Aluminium Case - 64Kg Roller assembly - 27Kg Threading Head Assembly - 24Kg Dimensions of Aluminium case - 780x580x400 Contents of case 1x Roller assembly 1x Threading head assembly 1x Instruction C.D 1x Instruction manual 1x Allen key 14mm 1x Allen key 10mm 1x Allen key 8mm 1x Allen key 3mm 1x Tommy bar 1x 5mm Packer plate 1x Hard point

 Open the catalog to page 5
UNIVERSAL SHEET PILE THREADER-6

USPT DAWSON CONSTRUCTION PLANT p-1 p-2

 Open the catalog to page 6
UNIVERSAL SHEET PILE THREADER-7

USPT DAWSON CONSTRUCTION PLANT INITIAL ASSEMBLY ON THE UNIT The new sheet pile threader is delivered packed inside a sturdy aluminium case. Before use the cross slide and vice assembly need to be fastened together, this is a simple case of sliding one into the other, but care must be taken to ensure that this is done the right way round. On the vice assembly a zero has been stamped on the lower edge, this should line up with the graduations on the cross slide support.

 Open the catalog to page 7
UNIVERSAL SHEET PILE THREADER-9

USPT DAWSON CONSTRUCTION PLANT SETTING THE ROLLERS TO FIT THE PILE SECTION Before the Universal Threader can be used it must first be accurately set-up for the type of pile that it’s to be used on. In order to do this it’s recommended that two lengths of pile are cut 1 approx.1000mm long and the other aprox.200mm, these must be straight, clean and free from any damage. Stage 1 is to set the rollers, 1 Release the swinging arm clamp bolt. (Picture 3) 2 Slacken the two roller units on the swinging arm. (Picture 4) 3 Screw the 2 pile thickness compensating screws fully in, these are found on the...

 Open the catalog to page 9
UNIVERSAL SHEET PILE THREADER-10

USPT DAWSON CONSTRUCTION PLANT p-8 p-9 p-10 When the roller unit has been set satisfactorily the next stage is to set the threading head, to work through the following steps, you will need an 8mm allen key and the tommy bar. 1 Make sure that the vice is not in its cocked position. (the cocking lever should be pointing upwards) (picture 20 , page 13) 2 Slacken the 6 clamp bolts. (Picture 8) 3 Slacken the bolts on the steady and the guide plates, the bolts for these parts have three positions to enable maximum adjustment, you may have to change the bolt positions later. 4 Engage the threading head...

 Open the catalog to page 10
UNIVERSAL SHEET PILE THREADER-11

USPT DAWSON CONSTRUCTION PLANT p-11 p-12 p-13 SETTING THE THREADING HEAD 8 It should now be possible to roll the unit up the pile, this will need 2 people, lift until the 2 piles disengage, then re-engage them and check their line-up, they should re-engage easily, the clutches should be perfectly lined up with clearance all round, if this is not the case then re-adjust the vice position or the position of the pile in the vice. 9 Set the vice stop by slackening the clamp bolt and pushing up against the pile. (Picture 12) 10 Set both steadies so that they are in light contact with the pile. (Picture...

 Open the catalog to page 11
UNIVERSAL SHEET PILE THREADER-13

USPT DAWSON CONSTRUCTION PLANT METHOD OF OPERATION When the setting procedure has been carried out satisfactorily do a final check that all bolts that were loosened during the setting procedure are tight. With this check done you can begin to thread piles by the following method. 1 Place the roller unit onto the driven or part driven pile with the swinging arm towards the pan of the pile, (if you are working on temporary works then you will need a bridging platform to stop the roller unit falling through,) tighten the roller clamp screw. 2 Place the threading head into the roller unit will the...

 Open the catalog to page 13
UNIVERSAL SHEET PILE THREADER-14

USPT DAWSON CONSTRUCTION PLANT

 Open the catalog to page 14
UNIVERSAL SHEET PILE THREADER-15

USPT DAWSON CONSTRUCTION PLANT SAFETY Because of the nature of sheet pilling it is possible to damage the sheet pile threader if not used as intended. A crane and a sheet pile can exert tremendous loads on the pile threader if any change to the pile verticality occurs once the pile is secured in the vice unit. Before hoisting the pile make sure that there are no obstructions to the rollers, check for damage, welded on brackets, bent sections, damaged clutches etc. these faults are common on previously used piles and can cause severe damage to the threader as the pile is hoisted. When positioning...

 Open the catalog to page 15

Archived catalogs

*Prices are pre-tax. They exclude delivery charges and customs duties and do not include additional charges for installation or activation options. Prices are indicative only and may vary by country, with changes to the cost of raw materials and exchange rates.