SHEET PILE CAPPING SYSTEMS OPERATOR INSTRUCTIONS & SPARE PARTS LIST
Open the catalog to page 1contacts WORLDWIDE DEALER NETWORK GLOBAL SUPPLY, LOCAL SUPPORT. Dawson Construction Plant Ltd Chesney Wold. Bleak Hall, Milton Keynes, MK6 1NE, England Tel: +44 (0) 1908 240300 Fax: +44 (0) 1908 240222 www.dcpuk.com...
Open the catalog to page 2Capping System Introduction The Redeb Support Bracket / The Multi-Pile Soffit Shutter Panel Limitations of the Redeb Bracket Safe Working Load / Angle of Sheet Pile Web / Fixing width Limitations of the Soffit Panels Installation of the Redeb Support Bracket Installation of the Soffit Panels Removal of the Soffit Panels Removal of the Redeb Support Bracket Torque Wrench Safety Points & Maintenance Technical Specification Location Buttons Component Parts Lists Soffit Panel (2.5m) / Redeb Bracket - RSB500 / 600 / 700 Redeb Bracket requirements for various sheet pile sections. Table 1 / Table...
Open the catalog to page 3EXPOSED PILE SECTION Scribe a setting out line for the RSB hard points 140mm below the bottom level of the cap. DAWSON'S REDEB SUPPORT BRACKET POSITIONED Lower brackets into position. Torque jacking bolts to 180Nm and level. DAWSON SOFIT PANELS POSITIONED Ensure at least 2 brackets support each panel. Lower the sofit panels into postion with the front edge tight against the pile.Use timber wedges, to drive the panel forward against the sheet pile face then lift and lock guard rail. (not shown)
Open the catalog to page 4SOFIT BARS Lightly tap ends of steel bars till they have push up hard against the contours of the sheet piles. SHUTTERING The side shutters can be positioned straight onto the sofit bars. FINISH Typically after 36 hours the soffit panels and redebs are ready to be removed.
Open the catalog to page 5The only purpose-made sheet pile capping system available is faster and more cost effective than any on-site ‘lash ups’. The Redeb Bracket and Soffit Panels can be assembled and re-used by unskilled labour. Welding or cutting of piles is not necessary. It renders obsolete the use of individual plywood soffit panels cut out to match pile pans. Traditional ‘old fashioned’ methods use brackets welded against piles to carry longitudinal beams and shuttering timber. Such brackets have ultimately to be burned off, their stubs ground down and the piles paintwork made good. All this trouble is...
Open the catalog to page 6Sheet piles are generally capped for Aesthetic purposes. The concrete cap serves to mask the inevitable irregularities in sheet pile length, penetration depth and line. They may also be used as a support for a railing or safety barrier. There are three models of Redeb bracket - the RSB500, RSB600 and RSB700. The RSB500 & RSB600 models are designed to work on both ‘Z’ type and ‘U’ type sheet pile sections. The RSB500 covering narrower pile sections than the RSB600. The RSB700 is exclusively designed to work with the Hoesch Larssen 700mm wide ‘U’ piles and Arcelor 750mm wide ‘U’ piles. With...
Open the catalog to page 7The soffit shutter panel consists of rectangular rods which are retained within a framework. The rods are free to slide within set limits. With the panel secured on the Redeb Bracket the rectangular bars are pushed towards the sheet piles, starting from the deepest part of each pile. The bars will deck out the soffit area and assume the shape of the sheet piles including the distortion which occurs during driving. The panels’ structural members, which retain the decking bars, are capable of carrying normal loads when supported on Redeb Brackets at ‘one-pair’ of pile centres. No additional...
Open the catalog to page 8limitations of the redeb bracket Although the Redeb Support Bracket is suitable in the majority of pile cap situations there are certain limitations which must be taken into account before specifying the equipment for any given job. (If in doubt consult the manufacturer). SAFE WORKING LOAD The S.W.L. of the Redeb is specified in terms of a point load on the bracket at a certain location i.e. a load applied on the arms of the bracket at a distance of 310mm from the centre of the Hard Points. (see page 21 for technical specification) a. Bracket fixed on interlocks of ‘U’ type sheet piles -...
Open the catalog to page 9The ‘Fixing Width’ is the distance between Hard Point tips when installed on any given sheet pile(s). Each Redeb model has a minimum achievable and maximum allowable ‘fixing width’ and this is different in both cases depending on whether 70° or 90° Hard Points are used. The maximum allowable fixing width must not be exceeded as this will lead to bracket damage and possible system collapse. THE JACKING BOLT SHOULD NEVER BE EXTENDED BY MORE THAN 77MM - MEASURE THE EXPOSED THREAD LENGTH IF IN DOUBT: Note: 1. There is a manufacturing tolerance on the above measurements of ±3mm. 2. For...
Open the catalog to page 10installations of the redeb support bracket 1. Scribe a setting out line at the correct height on the pan of every pile. Using a centre punch, mark the Hard Point positions on this line. Allow a distance of 40mm from the Hard Point centres to the top surface of the bracket. Allow a distance of 100mm for the thickness of the soffit panel i.e. a total of 140mm. Note: a. To save time this marking out procedure need only be done on every alternative pile pan. Intermediate brackets can then be positioned later using the installed brackets for reference. b. On sheet pile sections with particularly...
Open the catalog to page 11installations of the soffit pannel a. Position the Redebs as previously described in every outside pile pan. Ensure that they are at the correct level, correct torque (180 Newton metres) and horizontal (check with spirit level). b. Fix a ‘back stop’ inside the end of the longer arm of each Redeb Bracket and bolt it onto the Redeb using the M12 x 65 bolts and nuts provided. Back Stop Vertical Back Suppor
Open the catalog to page 12c. Lower the Soffit Panels using a 3 leg sling/chain connected to the lifting points as shown below onto the Redebs. Ensure where possible, that the front edge of the panel is tight up against the outside edge of the sheet piles. Ensure that at least 2 redebs are supporting each panel. Next, ensure that the back stops are as close to the rear of the Soffit Panel as possible. (These back stops prevent the Soffit Panels moving back along the Redebs and take any horizontal load that may try to cause such a movement). Use timber wedges, to drive the panel forward against the sheet pile face,...
Open the catalog to page 13All DAWSON CONSTRUCTION PLANT LIMITED catalogs and technical brochures
-
HPH2500
2 Pages
-
EMV550
2 Pages
-
EMV450
1 Pages
-
EMV220
1 Pages
-
HPH15Ke PILING HAMMER
2 Pages
-
HPH6500e PILING HAMMER
2 Pages
-
HPH4500e PILING HAMMER
2 Pages
-
HPH1800E PILING HAMMER
2 Pages
-
HPH1200 piling hammer
2 Pages
-
HPH2400E piling hammer
2 Pages
-
Hydraulic hammer power pack
2 Pages
-
Foundation piling
4 Pages
-
Push pull
8 Pages
-
Universal pile extractor
2 Pages
-
Sheet pile threader
4 Pages
-
Pipe lifting shoe 12 Tonne
2 Pages
-
steel handling shoes
2 Pages
-
Chain clamp
14 Pages
-
excavator mounted vibrators
2 Pages
-
Auger cleaners
4 Pages
-
UNIVERSAL PILE EXTRACTOR
2 Pages
-
UNIVERSAL SHEET PILE THREADER
28 Pages
-
HPH15K Piling hammer
2 Pages
-
EXCAVATOR MOUNTED DRILL
4 Pages
-
GROUND RELEASE SHACKLE
28 Pages
-
Hydraulic hammers
8 Pages
Archived catalogs
-
Sheet pile capping system
6 Pages