Push Thru Resistance
The push thru resistance of the installed rivet was defined using a specific method. This section outlines the procedure for assessing the resistance of rivets once installed.
Tensile Force
The tensile force of the installed rivet was measured using equipment compliant with the EN ISO 14589 standard. Detailed values can be found in the product data sheets.
BOLTOFIX™ Installation Settings
To ensure optimal installation of BOLTOFIX™, it is crucial to maintain the correct air pressure supply to the oleopneumatic tools. The minimum required pressure is 6 bars, which is standard for air pressure networks. It is recommended to use a pressure gauge to monitor this.
Shearing Resistance
The shearing resistance of the fitted rivet was measured using equipment compliant with the EN ISO 14589 standard. Values are available in the product data sheets.
Technical Data
BOLTOFIX™ Installation Process
BOLTOFIX™ should be installed using specific oleopneumatic or manual riveting tools. The use of a standard tool matching the BOLTOFIX™ diameter is essential. Detailed tool specifications are available in the TOOLIN'FIX™ data sheets.
Metal Sheet Preparation
Preparation of metal sheets according to their shape is crucial. For countersunk heads, a countersinking operation is necessary. No preparation is needed for standard heads.
Achievement Process
Four processes can be used to create the hole for BOLTOFIX™: punching, drilling, laser cutting, and water jet cutting. The quality of preparation is vital for optimal riveting and high mechanical resistance.
See more

Catalog excerpts

BOLTOFIX-1

Données techniques Technical data 4.9 / 5.1 Ce paramètre de réglage ne concerne que les appareils de pose oléopneumatiques. La pression d’alimentation conditionne l'effort de pose développé par l’appareil. La pression minimum requise est de 6 bars. Cette valeur correspond à la pression habituelle d’un réseau d’air comprimé. Pour garantir un rivetage optimum, il est conseillé d’équiper le réseau d’un manomètre de contrôle placé en amont de l’appareil de pose. This parameter concerns only oleopneumatic tools. The air supply pressure level determines the setting force of the installation tool. The minimum pressure required is 6 bars. This value corresponds to the usual pressure of an air pressure supply network. To guarantee optimum riveting, it is advise to use an air pressure gauge between the air supply and installation tool. Tensile force La tenue à la traction du rivet posé a été qualifiée avec l'équipement représenté ci-dessous, conformément à la norme EN ISO 14589. Valeurs consultables dans les fiches produits. Tensile force of the installed rivet was measured using the equipment shown below, in compliance with the EN ISO 14589 standard. Values are provided in the data sheets. Shearing resistance La tenue au cisaillement du rivet posé a été qualifiée avec l'équipement représenté ci-dessous, conformément à la norme EN ISO 14589. Valeurs consultables dans les fiches produits. To ensure optimal installation of BOLTOFIX™, the correct level of pressure supply to the equipment is essential. Pression d’alimentation Metal sheet preparation according to shape BOLTOFIX™ installation settings Corps / Body Réglages pour la pose de BOLTOFIX™ Afin de garantir la pose optimale de BOLTOFIX™, il est nécessaire de s’assurer de la pression d’alimentation de l’appareil. Préparation des tôles selon morphologie The shearing resistance of the fitted rivet was measured using the equipment shown below, in compliance with the EN ISO 14589 standard. Values are provided in the data sheets. Standard / Standard : unité : mm / dimensions: mm Tête / Head Standard / Standard : Pas de préparation de la tôle No workpiece preparation Fraisée / Countersunk : Réalisation d'un fraisage permettant de noyer la tête de BOLTOFIX™. Countersinking operation which allows the BOLTOFIX™ head to be integrated into workpiece. Achievement Process - Découpe laser Laser cutting Ces quatre processus peuvent être utilisés pour la réalisation du trou recevant BOLTOFIX™. Toutefois, la qualité de préparation est prépondérante pour garantir un rivetage optimal et donc une tenue mécanique élevée. These four processes can be used to create the hole destined to receive the BOLTOFIX™. Quality of preparation is, however, of overriding importance in guaranteeing optimal riveting which will result in high mechanical resistance. Installation tooling La pose de BOLTOFIX s’effectue à l’aide d'une riveteuse oléopneumatique (TFR104 ou TFR107) ou de la pince manuelle TFR304 disponibles dans la partie TOOLIN'FIX™. Pour permettre la pose, l’utilisation d’un outillage standard adapté au diamètre de BOLTOFIX™ est impérative. Riveting tool BOLTOFIX should be installed using the TFR104 or TFR107 oleopneumatic riveting tool or the TFR304 manual riveting tool, available in the TOOLIN'FIX™ section. Use of a standard tool matching the selected BOLTOFIX™ diameter is imperative to carrying out installation. Processus de pose de BOLTOFIX™ BOLTOFIX™ installation process Tenue au dénoyautage La tenue au dénoyautage du rivet posé a été qualifiée suivant la méthode ci-dessous. Pour le détail de chaque appareil, se reporter aux fiches TOOLIN'FIX™. For more details about all tools, please refer