TROLLEY ELITE FAST
13Pages

{{requestButtons}}

Catalog excerpts

TROLLEY ELITE FAST - 1

TROLLEY ELITE FAST PREMOUNTED CONDUCTOR LINE

Open the catalog to page 1
TROLLEY ELITE FAST - 2

The TROLLEY ELITE FAST line is particularly suitable for the distribution of electric power on machines such as cranes, overhead cranes and mobile machines in general, installed indoors or not exposed to bad weather (rain, water sprays..., etc.). TROLLEY ELITE FAST is a practical system, easy to install efficient, it requires minimum maintenance, and above all it is safe. The peculiarity of the ELITE FAST line is to have the PVC bar already complete with copper conductor, thus facilitating the assembly operations of the line. The “CE" marking affixed on the profile guarantees the conformity...

Open the catalog to page 2
TROLLEY ELITE FAST - 3

Working temperature Humidity Installation Pollution degree Installation altitude Max length with accessories (P 10)_ Mechanical resistance of the case Tensile strength on the suspensions Thermal resistance Trolley speed Corrosion-proof conductor Power supply 4 Poles Rated insulation voltage Impulse withstand voltage Rated coincidence factor Degree of protection BTS Leakage current _220 m/min Yes 140 A max, 380V, 50/60 Hz 3 + E (EARTH) 500V 6KV 1 IP20 Fixed, in the case < 0,5 m A MaterialNYLON BODY Small parts GALVANIZED STEEL Weight 90 g

Open the catalog to page 3
TROLLEY ELITE FAST - 4

Material Weight BLOCKING JOINT MaterialNYLON BODY Small parts GALVANIZED STEEL Weight 245 g an MaterialNYLON BODY Small parts GALVANIZED STEEL Weight 235 g

Open the catalog to page 4
TROLLEY ELITE FAST - 5

HEAD FEEDING Material NYLON BODY Small parts GALVANIZED STEEL INTERNAL FEEDING MaterialNYLON BODY Small parts GALVANIZED STEEL Weight 360 g TROLLEY (CURRENT COLLECTOR) Material NYLON BODY Small parts GALVANIZED STEEL Conductor material

Open the catalog to page 5
TROLLEY ELITE FAST - 6

SINGLE TOWING ARM DOUBLE TOWING ARM 285 MaterialGALVANIZED STEEL Weight 1800 g SUPPORT FOR TOWING ARMS Material Weight

Open the catalog to page 6
TROLLEY ELITE FAST - 7

Material Weight Material Weight BRACKET Material Weight 650 SPARE PARTS LOWER UPPER WHEEL WHEEL SPRING FOR SLIDING SHOE SLIDING SHOE

Open the catalog to page 7
TROLLEY ELITE FAST - 8

INTERNAL FEEDING LINE By CARPEL^ EXAMPLES OF FEEDING LINES HEAD FEEDING LINE

Open the catalog to page 8
TROLLEY ELITE FAST - 9

TROLLEY ELITE FAST LINE PRELIMINARY INSTRUCTIONS NECESSARY MATERIAL AND TOOLS 1. Assembly, installation, maintenance and dismantling operations must be carried out by qualified personnel only. 2. It is recommended to always and only work with the right lighting, avoiding shadow areas and dazzling lights. 3. It is mandatory to the personnel in charge for installation, maintenance or decommission of the system to use personal protective equipment, such as harnesses and gloves, as a precautionary measure. 4. The TROLLEY ELITE FAST line must be installed on machines equipped with at least one...

Open the catalog to page 9
TROLLEY ELITE FAST - 10

ASSEMBLY INSTRUCTIONS TROLLEY ELITE FAST LINE Place the suspensions P2 in the proper brackets, without completely tightening the nuts, to allow the correct alignment of the line. Insert the first profile bar into the suspensions and push upwards until the lower edges of the profile snap into the proper seats of the suspensions; insert the second bar in the same way. Join the copper phases by means of the clamp with screw provided, taking care to properly align the copper. Close the first junction by means of the joint P4 by fitting together the notches with the grooves on the ends of the...

Open the catalog to page 10
TROLLEY ELITE FAST - 11

TROLLEY ELITE FAST LINE Once all profile bars are mounted, place the head feeding box P6-FAST; - Connect the cable to the copper by means of the screws M6 provided and identify the phases with the labels provided (the earth phase is identified by a yellow band outside the profile, for the other phases copy the numbering present on the trolley P8). - Insert the closing plug on the profile. - Close the feeding box by joining the two halves by means of the screws and taking care to fit together the notches with the grooves on the ends of the profile and of the closing plug. Insert the trolley...

Open the catalog to page 11
TROLLEY ELITE FAST - 12

By CARPELS Install on the overhead crane the towing arm to be inserted on the trolley, to drag it along the entire line. In case of lines longer than 80m, it is advisable to use the expansion spring P10. The joint used for the spring must be placed on the last junction next to the closing end P5. In the case of multiple springs, one must always be placed on the last junction at the end of the line, and the others must be placed in order to equally divide the line in equal sections. - To install the spring P10: mount the joint P4 provided (this must not be fixed to the bracket), hook the...

Open the catalog to page 12
TROLLEY ELITE FAST - 13

Via Como, 79 23883 • BRIVIO (Lc) • Italy Phone +39 039 5320952 • www.bycarpel.it • info@ bycarpel.it GB0 by carpel

Open the catalog to page 13

All By CARPEL catalogs and technical brochures

  1. ATEX

    20 Pages

  2. TYPE 1800

    6 Pages

  3. Catalogue

    74 Pages