Installation and Operating Instructions Strainer Filter Type W Installation and Operating Instructions Stand 01/2014 © W-Filter W-FILTER Mohnweg 11 D-67346 Speyer Germany

 Open the catalogue to page 1

2.1 Marking of instructions in the manual 3 2.2 Non-compliance with safety instructions 3 2.4 Safety instructions for the operator / user 3 2.5 Safety instructions for maintenance, inspection and installation work 3 2.6 Unauthorized modification and manufacture of spare parts 4 2.7 Unauthorized modes of operation 4 10. Tightening process of flange screws / bolts 11

 Open the catalogue to page 2

Installation and Operating Instructions 1. General instructions This operating instruction applies to all strainers (W-Filter) as described in section 4. Only correct installation, maintenance or repair will ensure smooth operation of the strainers. The manufacturer shall not accept any liability if the instructions set forth in this manual are not complied with. The design, manufacture and testing of W-Filter strainers are subject to the European Pressure Equipment Directive 97/23/EC. Compliance with these requirements, however, is based on normal, static loading, e.g. - flow velocities typical...

 Open the catalogue to page 3

Installation and Operating Instructions 2. Safety These operating instructions contain fundamental information which must be complied with during installation, operation and maintenance. Not only must the general safety instructions laid down in this chapter on ”Safety” be complied with, but also the safety instructions outlined under specific headings. 2.1 Marking of instructions in the manual The safety instructions contained in this manual whose non-observance might cause hazards to persons are specially marked with the general hazard sign, Namely safety sign in accordance with DIN 4844 – W...

 Open the catalogue to page 4

Installation and Operating Instructions Generally, work on the strainer must only be carried out after the strainer has cooled down and strainer pressure has been released. The fluid temperature must be below the vaporization temperature limit in all areas in contact with the fluid. The shutdown procedure described in the manual for taking the strainer out of service must be adhered to without fail. Immediately following completion of the work, all safety-relevant and protective devices must be re-installed and / or re-activated. Please observe all instructions set out in section 6 Commissioning...

 Open the catalogue to page 5

Installation and Operating Instructions 4. Description of the Strainer Strainers are used for “cleaning of the flow medium” and serve the protection of pumps and other mobile plant parts. The strainer insert (sieve) is clamped between a dedicated clamping device for the sieve inside the strainer body, where it removes particles from the flow, depending on the mesh size selected. 4.1 Marking The strainers are marked in accordance with the Pressure Equipment Directive 97/23/EC. Marking includes as a minimum: manufacturer year of construction / fabrication number PN or max. permissible pressure/temperature...

 Open the catalogue to page 6

Installation and Operating Instructions 5. Installation Generally, the engineering contractor, construction company or operator / user are responsible for the positioning and installation of the strainer. 5.1 General Planning and installation errors may impair the reliable function of the strainer and pose a substantial safety hazard. Compliance with the following requirements is of particular importance: The piping must be laid such that detrimental thrust and torsion forces are kept away from the valve body during installation and operation to avoid both leakage and damage to the body. The caps...

 Open the catalogue to page 7

Installation and Operating Instructions 5.4 Installation instructions 5.4.1 Flanged valves The mating flange faces must be clean and undamaged. The gaskets on the mating flanges must be properly centered. Only fasteners and sealing elements made of approved materials shall be used. For the flange connection between strainer and pipe use all flange bolt holes provided. Use suitable tools to tighten the bolts evenly and crosswise at the permissible torques. 5.4.2 Welding instructions Responsibility for welding the valves into the piping, proper selection of approved welding consumables and any heat...

 Open the catalogue to page 8

Installation and Operating Instructions 7. Servicing / maintenance 7.1 Safety instructions Repair and maintenance work must only be performed by qualified personnel taking into account the relevant health and safety regulations. It is imperative that the below safety instructions and the general information on safety as per section 2, Safety, be observed for all servicing and maintenance work to be performed. Always use suitable spare parts and tools, even in emergencies, to ensure proper functioning of the strainers. 7.2 Maintenance All strainer components have been designed to be largely maintenance-free....

 Open the catalogue to page 9

Installation and Operating Instructions 9. Dismantling of the sieve (≤ DN500) ensure there is no pressure in the pipelines Let the system / medium cool down. Empty / vent the system from the medium. 1 3 4 7 5 after the pipeline is closed: 1. vent the strainer 2. empty the medium 3. unscrew the bolts of the cover 4. take-off the cover 5. unscrew the clamp device of the sieve 6. take-off the sieve and clean it 7. install sieve with new seal / gasket

 Open the catalogue to page 10

Installation and Operating Instructions 9. Dismantling of the sieve (≥ DN 500) ensure there is no pressure in the pipelines Let the system / medium cool down. Empty / vent the system from the medium. 4 1 2 after the pipeline is closed: 1. vent the strainer 2. empty the medium 3. unscrew the bolts of the cover 4. take-off the cover 5. unscrew the clamp device of the sieve 6. take-off the sieve and clean it 7. install sieve with new seal / gasket

 Open the catalogue to page 11

Installation and Operating Instructions 10. Tightening process of flange screws / bolts Having installed the sieve and the seal / gasket, the screws / bolts to close the cover shall be 1. tightened cross-wise 30% of the correct tightening torque, as illustrated below, 2. analogue to 1. tightened 60% of the correct tightening torque, 3. analogue to 1. tightened 100% of the correct tightening torque, 4. again tightened clock-wise at the correct tightening torque. This process must be repeated until no Repeat this process until the nuts cannot be turned any further. Check all bolted connections for...

 Open the catalogue to page 12